In January 2013, the project regarding the construction of  market in a different Gikondo has started but since then the market is still under construction. Local traders are wondering what made the construction delaying at this extent.

Only ten workers were present at the construction site
Only ten workers were present at the construction site

According  to the plan, the construction of the market  was supposed to be fully achieved within 15 months.

It is unfortunate for the traders to find out the construction  of the market is at its starting point.

Locals told the UM– USEKE reporter that the new location of the market challenges them in bringing goods to the market and to buyers are not familiar with the new place.

The roads are dusty, locals urged. Another concern is that the construction plan of the house has changed.

A certain Nkusi Eugene living in Kigarama cell expressed his concerns about the delay of the construction of the market.

One of the sellers in the market, Mukamana Cecilia since  1997 urged the persons  in charge of the construction to be clear and tell them exactly at which time the construction will end.

The manager of the market Bushishi Gaspard said that even him does not know at which exact time the  construction iof the market will take an end.

We have not be able to communicate withe the Construction company CABODI entrusted to build the market.

This is the Karugira cell where the new market is located
This is the Karugira cell where the new market is located
The plan that has been changed
The plan that has been changed